1 X 330 MW Thermal Power Plant
Inquire NowDescription
The Phase II Expansion Project of the 330 MW Thermal Power Plant in Uong Bi, Vietnam, represents a significant advancement in energy generation capabilities. Signed on April 11, 2008, this EPC Contract marks a pivotal development for the Uong Bi Thermal Power Plant, which serves as both the contract client and the ultimate owner. The project features a powerful 330 MW thermal power generator, designed to enhance the region’s energy supply.
The project officially commenced on May 4, 2008, and has progressed through various critical milestones, including a successful commencement ceremony and initial review meetings. As of the end of December 2008, the project achieved a general progress rate of 19.8%, with detailed advancements in engineering, procurement, and construction phases.
Specifications
Attribute | Details |
---|---|
Project Capacity | 1 x 330 MW |
Location | Uong Bi, Vietnam |
Contract Signing Date | April 11, 2008 |
Effective Date of EPC Contract | May 4, 2008 |
Project Progress (as of Dec 2008) | 19.8% |
Engineering Progress | 48.3% |
Procurement Progress | 23.7% |
Construction Progress | 2.5% |
Additional Information
Key milestones in the project timeline include:
- May 9, 2008 – Project group dispatched to the job site.
- May 23, 2008 – Commencement ceremony of the project.
- End of June 2008 – Project kick-off meeting in Chengdu.
- July 2008 – First review meeting in the task force office in Longquan District.
- August 2008 – Second review meeting in the task force office in Longquan District.
- December 26, 2008 – First piling ceremony at the job site.