1 X 330 MW Thermal Power Plant

Inquire Now

Description

The Phase II Expansion Project of the 330 MW Thermal Power Plant in Uong Bi, Vietnam, represents a significant advancement in energy generation capabilities. Signed on April 11, 2008, this EPC Contract marks a pivotal development for the Uong Bi Thermal Power Plant, which serves as both the contract client and the ultimate owner. The project features a powerful 330 MW thermal power generator, designed to enhance the region’s energy supply.

The project officially commenced on May 4, 2008, and has progressed through various critical milestones, including a successful commencement ceremony and initial review meetings. As of the end of December 2008, the project achieved a general progress rate of 19.8%, with detailed advancements in engineering, procurement, and construction phases.

Specifications

Attribute Details
Project Capacity 1 x 330 MW
Location Uong Bi, Vietnam
Contract Signing Date April 11, 2008
Effective Date of EPC Contract May 4, 2008
Project Progress (as of Dec 2008) 19.8%
Engineering Progress 48.3%
Procurement Progress 23.7%
Construction Progress 2.5%

Additional Information

Key milestones in the project timeline include:

  1. May 9, 2008 – Project group dispatched to the job site.
  2. May 23, 2008 – Commencement ceremony of the project.
  3. End of June 2008 – Project kick-off meeting in Chengdu.
  4. July 2008 – First review meeting in the task force office in Longquan District.
  5. August 2008 – Second review meeting in the task force office in Longquan District.
  6. December 26, 2008 – First piling ceremony at the job site.

Product Inquiry Form

Thanks your message successfully submitted.